Boston Building Permits: How the ISD Process Works

Boston building permits come from the Inspectional Services Department (ISD), and nearly every application now runs through one online portal. The two forms you will hear about are the Short Form, for smaller work that leaves the structure and use alone, and the Long Form, for work that changes either one. Pick the wrong one and you lose weeks. This guide walks through both, what they cost, how to look up a permit, what happens at inspection, and the extra approvals that zoning, historic districts and condo buildings can add.

Updated November 16, 2026 · Licensing & Permits

Boston runs its own building department, but it still enforces the Massachusetts State Building Code. What makes city of Boston permits different from most suburbs is the layering. Beyond ISD you may be dealing with the Zoning Board of Appeal, the Landmarks Commission or one of the historic district commissions, Parks and Recreation, and your condo association, each on its own track. If you understand the order those pieces happen in, the process is a lot less mysterious.

Boston building permits: Short Form or Long Form

ISD sorts most residential building work into two applications. Choosing correctly matters, because once you submit you cannot edit the application or upload more until ISD finishes its review.

The Short Form permit

The Short Form covers minor alterations that do not change a building’s structure or use. ISD’s examples include opening up a wall and making minor repairs or replacements. The City’s renovation guide uses a bathroom as the example: renovating an existing bathroom with no other structural changes is Short Form work.

The fee is $20 plus $10 for each $1,000 of estimated work cost, paid up front.

The Long Form permit

The Long Form covers major alterations or renovations that change the structure or the use. The renovation guide gives three common triggers: moving structural walls or egress, creating a new window, and adding or removing a doorway. Expanding a room, which some kitchen remodels do, is also one of the City’s examples.

Inside the portal you pick a Long Form type. ISD lists four:

  • Long Form/Alteration/Change of Occupancy, the most common, for structural work or a change in occupancy
  • Erect/New Construction, only for a new building on an empty lot
  • Amendment, only for changes to an existing Long Form application
  • Use of Premise, only for Use of Premise filings

Long Form applications need design plans stamped by a Massachusetts registered engineer or architect and a certified plot plan showing property lines and where the structure sits. If you do not have a plot plan, ISD says to hire a land surveyor. The fee is $50 plus $10 per $1,000 of estimated cost. A home addition or a new ADU changes the structure, which is the Long Form definition.

Trade permits are separate

Plumbing, electrical and sheet metal work each have their own permit, and the City requires a contractor with a valid, non-expired Massachusetts trade license to apply for them. Fire alarm or sprinkler changes need a fire protection engineer. The City’s guide for a bathroom remodel or kitchen lists plumbing and electrical permits right alongside the Short Form and Long Form.

Who can apply, and what you file

Homeowners and contractors can both apply for Short Form and Long Form permits, but with limits.

A homeowner can do the work personally only on an owner-occupied one or two family home. If you own a condo in a building with three or more homes, one floor of a three-decker for example, you must hire a contractor. Homeowners doing their own work file a description of the work, the estimated cost, a Homeowner Waiver and a Massachusetts workers’ compensation affidavit with Box 3 selected.

A contractor’s application has to be in the licensed contractor’s own name. For a Long Form, ISD says office staff may fill it out, but it must be in the contractor’s name and third-party submissions are not accepted. Contractors upload a copy of a valid trade license (front and back), a current certificate of liability insurance, the workers’ compensation affidavit, the signed contract with the homeowner, a Site Safety Plan Affidavit and a Mattocks-Higgins Affidavit of Workplace Safety. Some also need an experience rating form from their insurer. To check a contractor’s state license and registration before you get this far, see our guides to the Massachusetts construction supervisor license and the MA home improvement contractor lookup.

Applying through the ISD online portal

Every application, including ones started at the counter, goes through the ISD online portal. You create an account first, then apply. If you walk into 1010 Massachusetts Avenue, staff will still have you use the portal there. Payment online is by credit or debit card. In person, ISD also takes cash and checks.

Two snags come up often.

The first is the occupancy record. If the property does not have a Record of Occupancy, the portal shows “Please Confirm Occupancy.” Only the property owner can fix that, by calling ISD at 617-635-5300 to request a Confirmation of Occupancy inspection and being present for it. Contractors cannot schedule it, and no permit issues until it is resolved. Because the contractor usually discovers this only after applying, stay in touch with yours.

The second is outside approvals. Depending on the project you may need sign-off from Planning and Zoning, from Parks and Recreation for work within 100 feet of a park or parkway, or from the Landmarks Commission in a historic district. ISD is clear that you contact these agencies yourself. Once you have the approval, upload it to the portal, where it shows under the “Review” section.

ISD does not publish a standard processing time. Issuance depends on Planning and Zoning review and on whether you need to supply more information or approvals.

Do not start early

Work cannot begin before the permit is issued. ISD says starting early can mean paying double the permit cost or getting a building code violation. After issuance, work has to start within six months. Some projects can get a 180-day extension, but only certain project types qualify under the 2010 permit extension act.

Boston permit search and lookup

Several tools get lumped together as a Boston permit lookup or a City of Boston permit search, and they do different jobs. All of them sit under Inspectional Services, so a City of Boston Inspectional Services permit search and an ISD Boston permit search point to the same places.

  • Permit Finder (permitfinder.boston.gov) checks the status of a current Building or Fire permit application. This is what you use while waiting on your own permit.
  • The historical permit records search is an online document image search by address. ISD recommends Google Chrome for it. Building plans can only be viewed in person.
  • The City’s open data portal has a dataset of approved building permits issued after December 15, 2009, useful if you want to search Boston building permits across a street or neighborhood rather than one address.

So for a City of Boston permit search by address on an older house, start with the document image search, and plan an in-person visit to ISD if you need the drawings. If you are buying a house, a Boston ISD permit search is one way to check whether a finished basement or a roof deck was ever permitted.

Inspections

When the work is finished, you request an inspection by calling the ISD call center at 617-635-5300 or through the portal, either from Recent Activity or from Search My Permits. Have the permit number, the address, and the point of contact’s name and phone ready.

ISD says most projects need at least two inspections, a rough inspection near the start and a final at the end, and complex jobs need more. Footing and insulation inspections are among the types listed in the portal. An inspector contacts your point of contact within 48 hours to set a time. For contractor jobs the licensed contractor must be on site, and for electrical and plumbing permits the contact has to be a licensed contractor.

After a passed final, check that the permit shows as closed in the portal. If it still shows open, call ISD.

Zoning refusals and the Zoning Board of Appeal

If your plans do not comply with the Boston Zoning Code, ISD refuses the permit and you can ask the Zoning Board of Appeal (ZBA) for an exception. You can check your property’s zoning in advance with the City’s zoning viewer, and if you already expect to go to the ZBA, ISD asks for a nominal fee letter with the permit application.

The appeal rules, from the City’s ZBA filing page:

  1. File within 45 days of receiving your refusal letter, online, in person or through an agent at 1010 Massachusetts Avenue.
  2. Pay at filing. Residential buildings with three units or fewer pay a $150 flat fee. Other buildings, and residential buildings over three units, pay $150 for each City or state violation cited.
  3. Wait for the hearing date. The City publishes it at least 20 days ahead, mails notice, and runs it in the Boston Globe and Boston Herald. Neighboring owners, local officials and community groups may also be notified.
  4. Attend the public hearing yourself or send a representative. You may bring a lawyer, architect or other professional.
  5. Expect a formal decision notice roughly 15 days after the hearing.

The City’s planning agency reviews appeal applications and makes recommendations to the board, and it works with community groups and neighbors along the way. If the board approves, it may attach conditions such as engineer reports or more detailed plans, and you have to meet them for final approval. If it denies the appeal, you generally wait a year before trying again, unless you make major changes to the plans or the case was dismissed without prejudice.

Historic districts and landmarks

The Boston Landmarks Commission and 10 historic district commissions review changes in designated areas. They include the Back Bay Architectural District, the Historic Beacon Hill District, the South End Landmark District, the Bay Village Historic District, the Fort Point Channel Landmark District and several architectural conservation districts such as Aberdeen, Highland Park, Mission Hill Triangle, St. Botolph and Bay State Road/Back Bay West.

If your project is in one of them, you may need Landmarks Commission approval before ISD will issue the permit, and again, ISD will not request it on your behalf. Design review applications go through the Landmarks Commission’s online portal. Demolishing a building anywhere in Boston also requires an Article 85 demolition delay application first. If your plans change windows and doors, roofing or masonry on a building in a district, ask commission staff early whether review applies.

Condo buildings

Condo owners run into the unit-count rule more than anyone. Because homeowner work is limited to owner-occupied one and two family homes, a condo in a building with three or more homes needs a contractor for permitted work, even if you would be comfortable doing it yourself. The City permit also sits alongside whatever your condo documents require, so read your master deed and bylaws and talk to the board before you book a start date.

How Boston fits the statewide rules

The City handles its own permits, but the licensing and consumer rules come from the state. The homeowner exemption, the effect of pulling your own permit on the HIC Guaranty Fund, and permit rules in other towns are covered in our guide to whether a homeowner can pull a building permit in Massachusetts.

If you are planning a whole-home renovation or an addition in the city and want the permit path mapped before design starts, contact us with your address and scope.

This guide is general information for homeowners, not legal advice. Rules change and vary by city or town. Confirm details with your local building department or the state agency listed in the sources.

Common questions

Do I need a Short Form or a Long Form permit in Boston?

Short Form if the work is a minor alteration, repair or replacement that leaves the structure and use unchanged, such as renovating an existing bathroom without other structural changes. Long Form if you are changing the structure or use, for example moving a structural wall, adding a window opening or adding or removing a doorway. If you are unsure, ISD asks you to call 617-635-5300.

How do I do a City of Boston permit search by address?

For a current application, use the Permit Finder at permitfinder.boston.gov to check status. For older records, ISD offers an online document image search by address, and building plans can only be viewed in person at ISD. Permits approved since December 15, 2009 are also in the City's open data portal.

How much do Boston building permits cost?

The Short Form fee is $20 plus $10 for every $1,000 of estimated work cost. The Long Form fee is $50 plus $10 per $1,000. Fees are due when you apply. Starting work before the permit issues can cost you double the permit fee or a code violation.

Can I pull my own permit in Boston?

Only for work on an owner-occupied one or two family home. You file a Homeowner Waiver and a Massachusetts workers' compensation affidavit with your application. If your condo is in a building with three or more homes, such as one floor of a triple-decker, you have to hire a contractor.

How long does a Boston permit take?

ISD does not publish a fixed timeline. It depends on Planning and Zoning review and on whether you need to upload more information or outside approvals, such as Landmarks Commission sign-off in a historic district. A zoning appeal adds a public hearing on top.

What happens if ISD refuses my permit on zoning?

You can appeal to the Zoning Board of Appeal within 45 days of the refusal letter. The fee is $150 flat for a residential building with three units or fewer. The hearing date is published at least 20 days ahead and neighbors may be notified.

Who has to be at the final inspection?

For a contractor job, the licensed contractor must be on site. ISD says most projects need at least a rough inspection and a final inspection, and an inspector contacts your point of contact within 48 hours of the request.

Sources

Facts on this page were last checked against these sources on November 16, 2026.

  1. City of Boston, How to get a Short Form permit (accessed 2026-11-16)
  2. City of Boston, How to get a Long Form permit (accessed 2026-11-16)
  3. City of Boston, Renovate a bathroom or kitchen (accessed 2026-11-16)
  4. City of Boston, How to file an appeal with the Zoning Board (accessed 2026-11-16)
  5. City of Boston, Zoning Board of Appeal (accessed 2026-11-16)
  6. City of Boston, How to schedule an inspection (accessed 2026-11-16)
  7. City of Boston, How to find historical permit records (accessed 2026-11-16)
  8. City of Boston, Inspectional Services (accessed 2026-11-16)
  9. City of Boston, Landmarks Commission (accessed 2026-11-16)